News

Keeping you up to date with our ever changing industry.

Investee Company News

Update on Maamba Collieries Limited Thermal Power Plant

We are pleased to inform you that Unit 1 (150MW) of Maamba Collieries Coal Fired Power Plant (CFPP) was synchronized with the national grid yesterday, Sunday, 24 July 2016 at 12.57 hrs successfully.

Prior to this, Turbine 1 was rolled at 16.45 hrs on 23 July 2016 and the generator open circuit/short circuit/excitation system tests etc were conducted during the night on this day and 24 July in the morning.

ZCCM-IH owns 35% of Maamba Collieries Limited.

Previous ArticleNext Article